PROGRAM CAS145   S C H E D U L E   O F   E X T R A   W O R K    PAGE NO.  1
     DATE 02/07/18                                                  EST. NO. 005
     TIME 02:22 PM
     R.E. NAME: WASHINGTON, MARCUS                                     04-0P1504
     ---------------------------------------------------------------------------
     CCO REPORT       REPORT TYPE OF WORK(+) WORK  BR CONTR
     NO. NUMBER       AMOUNT PERFORMED   (-) DATE  WK RPT.NO C O M M E N T S
     ---------------------------------------------------------------------------
     001 0104       2,297.99 E.W. @ F.A.(+) 010318 N 0104.0
         0105       3,087.50                010418 N 0105.0
         0106       5,317.60                010518 N 0106.0
         0107       3,093.68                011118 N 0107.0
         0108       4,196.73                011218 N 0108.0
         0109      11,008.40                012018 N 0109.0
         0110          97.52                012018 N 0110.0
                   29,099.42  TOTAL THIS ESTIMATE
                  343,104.40  TOTAL PREVIOUS ESTIMATE
                  372,203.82  TOTAL TO DATE
     PROGRAM CAS145   S C H E D U L E   O F   D E D U C T I O N S    PAGE NO.  1
     DATE 02/07/18                                                  EST. NO. 005
     TIME 02:22 PM
     R.E. NAME: WASHINGTON, MARCUS                                     04-0P1504
     ---------------------------------------------------------------------------
     DEDUCTION DESCRIPTION          AMOUNT  EST           THIS           TOTAL
                                            NO.         ESTIMATE        ESTIMATE
     ---------------------------------------------------------------------------
     *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT ***
PROGRAM CAS145                                                                                                               PAGE  1
DATE 02/07/18                           STATE OF CALIFORNIA  -  DEPARTMENT OF TRANSPORTATION                               04-0P1504
TIME 02:22 PM                                                                                                       ESTIMATE NO. 005
BID OPENING 07/14/17                      P R O J E C T   R E C O R D  -  E S T I M A T E            WORK PERFORMED THROUGH 01/20/18
R.E. NAME:  WASHINGTON, MARCUS                                                                       DATE OF THIS ESTIMATE  02/07/18
        LOCATION                                        PROGRESS ESTIMATE
04-SM-92-0.9                                            -----------------
                                RGW CONSTRUCTION, INC.                                    IN SAN MATEO COUNTY, NEAR HALF MOON BAY,
                                550 GREENVILLE ROAD                                       AT 0.7 MILE EAST OF MAIN STREET
                                LIVERMORE, CA 94550
FED. AID NO.    N O N E
                                                                                          CONSTRUCT SOLDIER PILE WALL
------------------------------------------------------------------------------------------------------------------------------------
ITEM                                                   CONTRACT       ORIGINAL           THIS ESTIMATE               TOTAL ESTIMATE
NO.             ITEM DESCRIPTION             UNIT       PRICES       AUTH. AMT       QUANTITY     $ AMOUNT       QUANTITY     $ AMOU
------------------------------------------------------------------------------------------------------------------------------------
001 PAYMENT BOND PREMIUM                     LS       41,000.0000     41,000.00                                     0.000          0
PROGRAM CAS145                                                                                                               PAGE  2
DATE 02/07/18                           STATE OF CALIFORNIA  -  DEPARTMENT OF TRANSPORTATION                               04-0P1504
TIME 02:22 PM                                                                                                       ESTIMATE NO. 005
BID OPENING 07/14/17                      P R O J E C T   R E C O R D  -  E S T I M A T E            WORK PERFORMED THROUGH 01/20/18
R.E. NAME:  WASHINGTON, MARCUS                                                                       DATE OF THIS ESTIMATE  02/07/18
------------------------------------------------------------------------------------------------------------------------------------
ITEM                                                   CONTRACT       ORIGINAL           THIS ESTIMATE               TOTAL ESTIMATE
NO.             ITEM DESCRIPTION             UNIT       PRICES       AUTH. AMT       QUANTITY     $ AMOUNT       QUANTITY     $ AMOU
------------------------------------------------------------------------------------------------------------------------------------
    SUBTOTAL CONTRACT ITEMS                                                                         0.00                        0.00
         ADJUSTMENT OF COMPENSATION                                                                 0.00                        0.00
         EXTRA WORK                                                                            29,099.42                  372,203.82
    SUBTOTAL AMOUNT EARNED                                                                     29,099.42                  372,203.82
         ORIGINAL CONTRACT AMOUNT                                  41,000.00
    TOTAL WORK COMPLETED                                                                       29,099.42                  372,203.82
         MATERIALS ON HAND ON SITE                                                                                              0.00
         DEDUCTIONS                                                                                 0.00                        0.00
    TOTAL                                                                                      29,099.42                  372,203.82
             ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE
                              N O N E
DATE CONTR CONTRACT DATE WORK   BEGIN   EST.  DATE   WORKING   WEATHER NON-   C.C.O.       OTHER        PERCENT     PERCENT TIME
 APPROVED    DAYS    STARTED   CONSTR   COMPLETION    DAYS     WORKING DAYS    DAYS        DAYS        COMPLETED       ELAPSED
  07/14/17     120   07/15/17  07/15/17  03/30/18        56         69            0           0             19%            47%
                                                                                                         PROGRESS IS SATISFACTORY
                                                                                  WASHINGTON, MARCUS
                                                                                  RESIDENT ENGINEER
     PROGRAM CAS145                                                             
     DATE 02/07/18