PROGRAM CAS145   S C H E D U L E   O F   E X T R A   W O R K    PAGE NO.  1
     DATE 08/24/09                                                    EST. NO.01
     TIME 02:56 PM
     R.E. NAME: RONALD SANGALANG                                       04-1E3804
     ---------------------------------------------------------------------------
     CCO REPORT       REPORT TYPE OF WORK(+) WORK  BR CONTR
     NO. NUMBER       AMOUNT PERFORMED   (-) DATE  WK RPT.NO C O M M E N T S
     ---------------------------------------------------------------------------
     *** THERE ARE NO EXTRA WORK PAYMENTS THIS ESTIMATE ***
     PROGRAM CAS145   S C H E D U L E   O F   D E D U C T I O N S    PAGE NO.  1
     DATE 08/24/09                                                    EST. NO.01
     TIME 02:56 PM
     R.E. NAME: RONALD SANGALANG                                       04-1E3804
     ---------------------------------------------------------------------------
     DEDUCTION DESCRIPTION          AMOUNT  EST           THIS           TOTAL
                                            NO.         ESTIMATE        ESTIMATE
     ---------------------------------------------------------------------------
     *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT ***
PROGRAM CAS145                                                                                                               PAGE  1
DATE 08/24/09                           STATE OF CALIFORNIA  -  DEPARTMENT OF TRANSPORTATION                               04-1E3804
TIME 02:56 PM                                                                                                        ESTIMATE NO. 01
BID OPENING 06/17/09                      P R O J E C T   R E C O R D  -  E S T I M A T E            WORK PERFORMED THROUGH 08/20/09
R.E. NAME:  RONALD SANGALANG                                                                         DATE OF THIS ESTIMATE  08/24/09
        LOCATION                                        PROGRESS ESTIMATE
04-NAP-29-38.1/48.6                                     -----------------
                                FEDCO CONSTRUCTION, INC                                   IN NAPA COUNTY NEAR CALISTOGA FROM
                                ATTN. FRANK RELENDE                                       0.2 MILE NORTH OF SILVERADO TRAIL
                                3510 BROOKS AVENUE                                        TO LAKE COUNTY LINE
                                SANTA ROSA, CA 95407
FED. AID NO. SARR-P029(105)E  ,A-P029(105)E
                                                                                          COLD PLANE ASPHALT CONCRETE
------------------------------------------------------------------------------------------------------------------------------------
ITEM                                                   CONTRACT     ORIGINAL           THIS ESTIMATE               TOTAL ESTIMATE
NO.             ITEM DESCRIPTION             UNIT       PRICES     AUTH. AMT       QUANTITY     $ AMOUNT       QUANTITY     $ AMOUNT
------------------------------------------------------------------------------------------------------------------------------------
01 SMALL BUSINESS UTILIZATION REPORT        EA        250.0000        250.00                                     0.000          0.00
02 CONSTRUCTION SITE MANAGEMENT             LS      5,000.0000      5,000.00         0.300     1,500.00          0.300      1,500.00
03 PREPARE WATER POLLUTION CONTROL          LS        670.0000        670.00         0.750       502.50          0.750        502.50
   PROGRAM
04 TEMPORARY DRAINAGE INLET PROTECTION      EA        275.0000      2,750.00        10.000     2,750.00         10.000      2,750.00
05 STREET SWEEPING                          LS      9,600.0000      9,600.00         0.200     1,920.00          0.200      1,920.00
06 CONSTRUCTION AREA SIGNS                  LS      3,800.0000      3,800.00         0.700     2,660.00          0.700      2,660.00
07 TRAFFIC CONTROL SYSTEM                   LS     16,000.0000     16,000.00         0.200     3,200.00          0.200      3,200.00
08 PORTABLE CHANGEABLE MESSAGE SIGN         EA      1,600.0000      3,200.00         2.000     3,200.00          2.000      3,200.00
09 COLD PLANE ASPHALT CONCRETE PAVEMENT     SQYD        3.6000     47,520.00     3,060.000    11,016.00      3,060.000     11,016.00
10 SEAL RANDOM CRACKS                       LNMI    2,700.0000     40,500.00                                     0.000          0.00
11 HOT MIX ASPHALT (TYPE A)                 TON       101.0000    347,440.00       765.000    77,265.00        765.000     77,265.00
12 DATA CORE                                LS      1,875.0000      1,875.00                                     0.000          0.00
13 TACK COAT                                TON     1,200.0000      7,200.00         0.950     1,140.00          0.950      1,140.00
14 4" THERMOPLASTIC TRAFFIC STRIPE          LF          0.4000     10,680.00                                     0.000          0.00
15 THERMOPLASTIC PAVEMENT MARKING           SQFT        9.0000      2,700.00                                     0.000          0.00
16 4" THERMOPLASTIC TRAFFIC STRIPE          LF          0.5500      1,034.00                                     0.000          0.00
   (BROKEN 17-7)
17 PAVEMENT MARKER (RETROREFLECTIVE)        EA         10.5000      1,995.00                                     0.000          0.00
18 PAVEMENT MARKER                          EA         12.5000      7,375.00                                     0.000          0.00
   (RETROREFLECTIVE-RECESSED)
PROGRAM CAS145                                                                                                               PAGE  2
DATE 08/24/09                           STATE OF CALIFORNIA  -  DEPARTMENT OF TRANSPORTATION                               04-1E3804
TIME 02:56 PM                                                                                                        ESTIMATE NO. 01
BID OPENING 06/17/09                      P R O J E C T   R E C O R D  -  E S T I M A T E            WORK PERFORMED THROUGH 08/20/09
R.E. NAME:  RONALD SANGALANG                                                                         DATE OF THIS ESTIMATE  08/24/09
------------------------------------------------------------------------------------------------------------------------------------
ITEM                                                   CONTRACT     ORIGINAL           THIS ESTIMATE               TOTAL ESTIMATE
NO.             ITEM DESCRIPTION             UNIT       PRICES     AUTH. AMT       QUANTITY     $ AMOUNT       QUANTITY     $ AMOUNT
------------------------------------------------------------------------------------------------------------------------------------
    SUBTOTAL CONTRACT ITEMS                                                                   105,153.50                  105,153.50
         ADJUSTMENT OF COMPENSATION                                                                 0.00                        0.00
         EXTRA WORK                                                                                 0.00                        0.00
    SUBTOTAL AMOUNT EARNED                                                                    105,153.50                  105,153.50
         ORIGINAL CONTRACT AMOUNT                                 509,589.00
    TOTAL WORK COMPLETED                                                                      105,153.50                  105,153.50
         MATERIALS ON HAND ON SITE                                                                                              0.00
         MATERIALS ON HAND ELSEWHERE                                                                                            0.00
         DEDUCTIONS                                                                                 0.00                        0.00
    TOTAL                                                                                     105,153.50                  105,153.50
             ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE
                              N O N E
DATE CONTR CONTRACT DATE WORK   BEGIN   EST.  DATE   WORKING   WEATHER NON-   C.C.O.       OTHER        PERCENT     PERCENT TIME
 APPROVED    DAYS    STARTED   CONSTR   COMPLETION    DAYS     WORKING DAYS    DAYS        DAYS        COMPLETED       ELAPSED
  07/16/09      40   08/05/09  08/05/09  06/30/08        13          0            0           0             21%            33%
                                                                                                         PROGRESS IS SATISFACTORY
                                                                                  RONALD SANGALANG
                                                                                  RESIDENT ENGINEER
     PROGRAM CAS145                                                             