PROGRAM CAS145   S C H E D U L E   O F   E X T R A   W O R K    PAGE NO.  1
     DATE 01/18/19                                                  EST. NO. 009
     TIME 06:51 AM
     R.E. NAME: ATAKO, KINGSTON                                        04-3G3054
     ---------------------------------------------------------------------------
     CCO REPORT       REPORT TYPE OF WORK(+) WORK  BR CONTR
     NO. NUMBER       AMOUNT PERFORMED   (-) DATE  WK RPT.NO C O M M E N T S
     ---------------------------------------------------------------------------
     001 0001      48,973.83 E.W. @ L.S.(+) 010319 N 001-01
     002 0001     199,500.00 A.C. @ L.S.(+) 010319 N 002-01
                  248,473.83  TOTAL THIS ESTIMATE
                        0.00  TOTAL PREVIOUS ESTIMATE
                  248,473.83  TOTAL TO DATE
     PROGRAM CAS145   S C H E D U L E   O F   D E D U C T I O N S    PAGE NO.  1
     DATE 01/18/19                                                  EST. NO. 009
     TIME 06:51 AM
     R.E. NAME: ATAKO, KINGSTON                                        04-3G3054
     ---------------------------------------------------------------------------
     DEDUCTION DESCRIPTION          AMOUNT  EST           THIS           TOTAL
                                            NO.         ESTIMATE        ESTIMATE
     ---------------------------------------------------------------------------
     *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT ***
PROGRAM CAS145                                                                                                               PAGE  1
DATE 01/18/19                           STATE OF CALIFORNIA  -  DEPARTMENT OF TRANSPORTATION                               04-3G3054
TIME 06:51 AM                                                                                                       ESTIMATE NO. 009
BID OPENING 08/24/17                      P R O J E C T   R E C O R D  -  E S T I M A T E            WORK PERFORMED THROUGH 01/20/19
R.E. NAME:  ATAKO, KINGSTON                                                                          DATE OF THIS ESTIMATE  01/18/19
        LOCATION                                     RERUN PROGRESS ESTIMATE
04-SM-92-15.3/15.5                                   -----------------------
04-ALA-92-R0.0/R1.6             BLEYCO INCORPORATED                                       IN THE CITY AND COUNTY OF SAN
04-SF-80-R5.5/R8.8              11425 CULL CANYON ROAD                                    FRANCISCO AND SAN MATEO COUNTY AT
                                CASTRO VALLEY  CA 94552                                   VARIOUS LOCATIONS
FED. AID NO.    N O N E
                                                                                          REPLACE THE EXISTING FOG-HORNS,
------------------------------------------------------------------------------------------------------------------------------------
ITEM                                                   CONTRACT       ORIGINAL           THIS ESTIMATE               TOTAL ESTIMATE
NO.             ITEM DESCRIPTION             UNIT       PRICES       AUTH. AMT       QUANTITY     $ AMOUNT       QUANTITY     $ AMOU
------------------------------------------------------------------------------------------------------------------------------------
001 LEAD COMPLIANCE PLAN                     LS        5,000.0000      5,000.00                                     0.500      2,500
002 CONSTRUCTION AREA SIGNS                  LS       15,000.0000     15,000.00                                     0.500      7,500
003 TRAFFIC CONTROL SYSTEM                   LS      126,750.0000    126,750.00         0.242    30,673.50          0.796    100,893
004 PORTABLE CHANGEABLE MESSAGE SIGN (LS)    LS       10,000.0000     10,000.00                                     0.820      8,200
005 JOB SITE MANAGEMENT                      LS       50,000.0000     50,000.00         0.080     4,000.00          0.916     45,800
006 PREPARE WATER POLLUTION CONTROL PROGRAM  LS        5,000.0000      5,000.00                                     1.000      5,000
007 NAVIGATIONAL LIGHTS                      LS    1,660,264.0000  1,660,264.00                                     0.948  1,573,930
    (SAN FRANCISCO-OAKLAND BAY BRIDGE)
008 NAVIGATIONAL LIGHTS (SAN MATEO BRIDGE)   LS      328,509.0000    328,509.00         0.054    17,739.49          1.000    328,509
009 FOGHORN (SAN MATEO BRIDGE)               LS       56,586.0000     56,586.00         0.065     3,678.09          0.973     55,058
010 NAVIGATIONAL LIGHTS (DUMBARTON BRIDGE)   LS      114,367.0000    114,367.00         0.052     5,947.08          0.999    114,252
011 FOGHORN (DUMBARTON BRIDGE)               LS       56,586.0000     56,586.00         0.065     3,678.09          0.973     55,058
012 CONNECTION TO EXISTING SCADA             LS       74,247.0000     74,247.00                                     0.259     19,229
    (SAN FRANCISCO-OAKLAND BAY BRIDGE)
013 CONNECTION TO EXISTING SCADA             LS       74,247.0000     74,247.00                                     0.000          0
    (SAN MATEO BRIDGE)
014 CONNECTION TO EXISTING SCADA             LS       74,247.0000     74,247.00                                     0.000          0
    (DUMBARTON BRIDGE)
015 MARINE RADAR BEACON                      LS      321,523.0000    321,523.00                                     0.690    221,850
    (SAN FRANCISCO-OAKLAND BAY BRIDGE)
016 MARINE RADAR BEACON                      LS       85,425.0000     85,425.00         0.087     7,431.98          1.000     85,425
    (SAN MATEO BRIDGE)
017 EXISTING SYSTEMS REMOVAL                 LS       35,775.0000     35,775.00                                     0.967     34,594
    (SAN FRANCISCO-OAKLAND BAY BRIDGE)
018 EXISTING SYSTEMS REMOVAL                 LS       28,332.0000     28,332.00                                     1.000     28,332
    (SAN MATEO BRIDGE)
019 EXISTING SYSTEMS REMOVAL                 LS       15,560.0000     15,560.00                                     1.000     15,560
    (DUMBARTON BRIDGE)
020 MAINTAINING EXISTING AND TEMPORARY       LS      268,505.0000    268,505.00         0.080    21,480.40          0.916    245,950
    ELECTRICAL SYSTEM
PROGRAM CAS145                                                                                                               PAGE  2
DATE 01/18/19                           STATE OF CALIFORNIA  -  DEPARTMENT OF TRANSPORTATION                               04-3G3054
TIME 06:51 AM                                                                                                       ESTIMATE NO. 009
BID OPENING 08/24/17                      P R O J E C T   R E C O R D  -  E S T I M A T E            WORK PERFORMED THROUGH 01/20/19
R.E. NAME:  ATAKO, KINGSTON                                                                          DATE OF THIS ESTIMATE  01/18/19
------------------------------------------------------------------------------------------------------------------------------------
ITEM                                                   CONTRACT       ORIGINAL           THIS ESTIMATE               TOTAL ESTIMATE
NO.             ITEM DESCRIPTION             UNIT       PRICES       AUTH. AMT       QUANTITY     $ AMOUNT       QUANTITY     $ AMOU
------------------------------------------------------------------------------------------------------------------------------------
    SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION                                               94,628.63                2,947,644.11
         ADJUSTMENT OF COMPENSATION                                                           199,500.00                  199,500.00
         EXTRA WORK                                                                            48,973.83                   48,973.83
    SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION                                               343,102.46                3,196,117.94
021 MOBILIZATION                             LS      340,000.0000    340,000.00                                     1.000    340,000
         ORIGINAL CONTRACT AMOUNT                               3,745,923.00
    TOTAL WORK COMPLETED                                                                      343,102.46                3,536,117.94
         MATERIALS ON HAND ON SITE                                                                                              0.00
         DEDUCTIONS                                                                                 0.00                        0.00
    TOTAL                                                                                     343,102.46                3,536,117.94
             ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE
                              N O N E
DATE CONTR CONTRACT DATE WORK   BEGIN   EST.  DATE   WORKING   WEATHER NON-   C.C.O.       OTHER        PERCENT     PERCENT TIME
 APPROVED    DAYS    STARTED   CONSTR   COMPLETION    DAYS     WORKING DAYS    DAYS        DAYS        COMPLETED       ELAPSED
  11/30/17     250   01/29/18  01/29/18  01/29/19       244          0            0           0             89%            98%
                                                                                                         PROGRESS IS SATISFACTORY
                                                                                  ATAKO, KINGSTON
                                                                                  RESIDENT ENGINEER
     PROGRAM CAS145                                                             
     DATE 01/18/19