Dept. of Trans.            SEMI-FINAL             Serial No.    Contract No.
                                                  23-235-11-21  01-0G2104
                    PROGRESS PAYMENT VOUCHER      %complete:    %time:
                                                   100%          100%

Location:                                         Federal Project:
01-DN-101-21.2                                    ACNH-Q101(392)

Progress payment No. 022                     Payment period ending: 05-30-23
MCCULLOUGH CONSTRUCTION INC
57 ALDER GROVE RD
ARCATA CA 95521

Escrow No. 00000
                                           Total Estimate      This Estimate
 1. Contract Itms Without Mobil.             7,463,943.85          38,584.35
 2. a. Extra Work                               67,514.67          36,433.77
    b. Adustment Comp.                          13,659.33          13,659.33
 3. Materials on Hand
 4. Earned Subject to Retention              7,545,117.85          88,677.45
 5. Mobilization                               838,646.00               0.00
 6. Total Work Completed      8,383,763.85
 7. Deductions                                       0.00          22,000.00
 8. a. Contract Retentions
    b. Unsatisfactory Retentions
    c. Reduction after 95% Comp.
 9. Total pay to Contractor                  8,383,763.85         110,677.45
10. Reduction Amt to Escrow
11. Payment to Escrow                 0.00
12. Net Pymt. this Estimate                                       110,677.45