Dept. of Trans. PROGRESS Serial No. Contract No. 25-199-10-09 01-0H6104 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 51% Location: Federal Project: 01-HUM-36-13.5/R36.1 ACNH-S036(119) Progress payment No. 016 Payment period ending: 07-20-25 MERCER FRASER COMPANY PO BOX 1006 EUREKA CA 95502-1006 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,544,065.70 1,387,816.69 2. a. Extra Work b. Adustment Comp. 98,239.84 0.00 3. Materials on Hand 1,151,700.00 -152,889.00 4. Earned Subject to Retention 26,794,005.54 1,234,927.69 5. Mobilization 3,669,811.90 0.00 6. Total Work Completed 29,312,117.44 7. Deductions -4,000.00 40,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,459,817.44 1,274,927.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,274,927.69