Dept. of Trans.       AFTER ACCEPTANCE   Serial No.  Contract No.                       
                                          10-194-10-50  02-1E1104                       
                PROGRESS PAYMENT VOUCHER  %complete:   %time:                           
Location:                                 100%         100%                             
02-SHA-5-R28.9/R29.3                    Federal Project:                                
                                     ACHS-058(339)                                      
                             IM-058(339)                                                
                                                                                        
Progress payment No. 05            Payment period ending: 06-21-10                      
J F SHEA CONSTRUCTION INC                                                               
P O BOX 494519                                                                          
REDDING CA 96049                                                                        
                                                                                        
                                                                                        
Escrow No.  00000                                                                       
                                    Total Estimate   This Estimate                      
1. Contract Itms Without Mobil.       1,519,768.09       27,613.34                      
2.a. Extra Work                          10,737.89        7,893.89                      
  b. Adjustment Comp.                   150,271.18        8,608.18                      
3. Materials on Hand                                                                    
4. Earned Subject to Retention        1,680,777.16       44,115.41                      
5. Mobilization                                                                         
6. Total Work Completed    1,680,777.16                                                 
7. Deductions                           -12,761.33      -12,761.33                      
8. a.Contract Retentions                                                                
   b. Unsatisfactory Prog.                                                              
   c. Reduction after 95% Comp.                                                         
9. Total pay to Contractor            1,668,015.83       31,354.08                      
10. Reduction Amt to Escrow                                                             
11. Payment to Escrow             0.00                                                  
12. Net Pymt. this Estimate                              31,354.08