Dept. of Trans. PROGRESS Serial No. Contract No. 25-232-14-40 02-1J75U4 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 29% Location: Federal Project: 02-LAS-36-14.4/R16.8 HSNH-S036(121) Progress payment No. 004 Payment period ending: 08-20-25 HAT CREEK CONSTRUCTION & MATERIALS INC 24339 STATE HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,834,035.52 1,234,947.61 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 241,798.64 -11,588.50 4. Earned Subject to Retention 2,075,834.16 1,223,359.11 5. Mobilization 1,031,250.00 343,750.00 6. Total Work Completed 2,865,285.52 7. Deductions -391,777.28 -391,777.28 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,715,306.88 1,175,331.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,175,331.83