Dept. of Trans. PROGRESS Serial No. Contract No. 10-223-08-05 02-377814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 42% 02-PLU-70-R79.1/ .0 Federal Project: NONE Progress payment No. 06 Payment period ending: 07-20-10 R E M CONSTRUCTION INCORPORATED 6621 CLARK ROAD PARADISE CA 95969 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 470,248.32 116,311.38 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 470,248.32 116,311.38 5. Mobilization 6. Total Work Completed 470,248.32 7. Deductions -20,940.43 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 449,307.89 116,311.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 116,311.38