Dept. of Trans.             PROGRESS              Serial No.    Contract No.
                                                  21-204-16-05  02-4G41U4
                    PROGRESS PAYMENT VOUCHER      %complete:    %time:
                                                    91%           98%

Location:                                         Federal Project:
02-SHA-5-56.6/67.0                                B1IM-005-8(362)

Progress payment No. 016                     Payment period ending: 07-20-21
J F SHEA CONSTRUCTION INC
PO BOX 494519
REDDING CA 960494519

Escrow No. 00000
                                           Total Estimate      This Estimate
 1. Contract Itms Without Mobil.            12,460,004.66         470,072.75
 2. a. Extra Work                              266,423.64             325.00
    b. Adustment Comp.                          89,341.04               0.00
 3. Materials on Hand                           11,865.00               0.00
 4. Earned Subject to Retention             12,827,634.34         470,397.75
 5. Mobilization                             1,400,000.00               0.00
 6. Total Work Completed     14,215,769.34
 7. Deductions                                 -61,500.00          10,000.00
 8. a. Contract Retentions
    b. Unsatisfactory Retentions
    c. Reduction after 95% Comp.
 9. Total pay to Contractor                 14,166,134.34         480,397.75
10. Reduction Amt to Escrow
11. Payment to Escrow                 0.00
12. Net Pymt. this Estimate                                       480,397.75