Dept. of Trans. SEMI-FINAL Serial No. Contract No. 25-196-09-20 03-1H1304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-SOL-12-26.2/26.4 NONE 03-SAC-12-0.0/0.5 Progress payment No. 010 Payment period ending: 02-19-25 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,919,007.77 0.00 2. a. Extra Work 219,143.37 2,206.70 b. Adustment Comp. 69,268.12 3,399.68 3. Materials on Hand 4. Earned Subject to Retention 5,207,419.26 5,606.38 5. Mobilization 540,555.00 0.00 6. Total Work Completed 5,747,974.26 7. Deductions 0.00 22,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,747,974.26 27,606.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,606.38