Dept. of Trans.             PROGRESS              Serial No.    Contract No.
                                                  23-293-13-28  03-2G7504
                    PROGRESS PAYMENT VOUCHER      %complete:    %time:
                                                    95%           75%

Location:                                         Federal Project:
03-GLE-45-7.0/23.2                                NONE

Progress payment No. 003                     Payment period ending: 10-20-23
KNIFE RIVER CONSTRUCTION
1764 SKYWAY
CHICO CA 95928

Escrow No. 00000
                                           Total Estimate      This Estimate
 1. Contract Itms Without Mobil.             4,795,158.60       2,728,397.44
 2. a. Extra Work                            1,573,530.00       1,573,530.00
    b. Adustment Comp.
 3. Materials on Hand
 4. Earned Subject to Retention              6,368,688.60       4,301,927.44
 5. Mobilization                               217,000.00          10,850.00
 6. Total Work Completed      6,585,688.60
 7. Deductions                                -177,000.00        -177,000.00
 8. a. Contract Retentions
    b. Unsatisfactory Retentions
    c. Reduction after 95% Comp.
 9. Total pay to Contractor                  6,408,688.60       4,135,777.44
10. Reduction Amt to Escrow
11. Payment to Escrow                 0.00
12. Net Pymt. this Estimate                                     4,135,777.44