Dept. of Trans.             PROGRESS              Serial No.    Contract No.
                                                  24-200-13-20  04-0K6304
                    PROGRESS PAYMENT VOUCHER      %complete:    %time:
                                                    58%           14%

Location:                                         Federal Project:
04-NAP-29-16.4/19.0                               NONE

Progress payment No. 008                     Payment period ending: 07-20-24
GORDON N BALL INC
333 CAMILLE AVE
ALAMO CA 94507

Escrow No. 00000
                                           Total Estimate      This Estimate
 1. Contract Itms Without Mobil.             1,623,456.00         377,015.00
 2. a. Extra Work                              101,223.47          33,062.56
    b. Adustment Comp.
 3. Materials on Hand
 4. Earned Subject to Retention              1,724,679.47         410,077.56
 5. Mobilization                               320,000.00          16,000.00
 6. Total Work Completed      2,044,679.47
 7. Deductions
 8. a. Contract Retentions
    b. Unsatisfactory Retentions
    c. Reduction after 95% Comp.
 9. Total pay to Contractor                  2,044,679.47         426,077.56
10. Reduction Amt to Escrow
11. Payment to Escrow                 0.00
12. Net Pymt. this Estimate                                       426,077.56