Dept. of Trans.             PROGRESS              Serial No.    Contract No.
                                                  22-048-16-43  04-4J7304
                    PROGRESS PAYMENT VOUCHER      %complete:    %time:
                                                    91%           89%

Location:                                         Federal Project:
04-ALA-880-20.9/20.9                              HSIM-8801(911)

Progress payment No. 011                     Payment period ending: 02-20-22
TEICHERT CONSTRUCTION
3500 AMERICAN RIVER DRIVE
SACRAMENTO CA 95864

Escrow No. 00000
                                           Total Estimate      This Estimate
 1. Contract Itms Without Mobil.             2,387,959.20             808.26
 2. a. Extra Work                              155,553.85          44,139.68
    b. Adustment Comp.
 3. Materials on Hand
 4. Earned Subject to Retention              2,543,513.05          44,947.94
 5. Mobilization                               247,000.00               0.00
 6. Total Work Completed      2,790,513.05
 7. Deductions                                  -1,000.00               0.00
 8. a. Contract Retentions
    b. Unsatisfactory Retentions
    c. Reduction after 95% Comp.
 9. Total pay to Contractor                  2,789,513.05          44,947.94
10. Reduction Amt to Escrow
11. Payment to Escrow                 0.00
12. Net Pymt. this Estimate                                        44,947.94