Dept. of Trans. PROGRESS Serial No. Contract No. 25-203-13-52 05-1C9504 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 25% Location: Federal Project: 05-SB-101-R36.0/R37.0 BFNH-Q101(424) Progress payment No. 010 Payment period ending: 07-20-25 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,335,826.81 664,824.50 2. a. Extra Work 12,476.47 350.00 b. Adustment Comp. 3. Materials on Hand 1,846,157.00 -241.94 4. Earned Subject to Retention 9,194,460.28 664,932.56 5. Mobilization 3,937,500.00 0.00 6. Total Work Completed 11,285,803.28 7. Deductions -9,228.97 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,122,731.31 658,932.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 658,932.56