Dept. of Trans. PROGRESS Serial No. Contract No. 25-199-13-13 05-1J9704 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 24% Location: Federal Project: 05-SLO-58-1.8/6.9 NONE Progress payment No. 002 Payment period ending: 07-20-25 CALPORTLAND CONSTRUCTION PO BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 617,827.10 243,376.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 617,827.10 243,376.40 5. Mobilization 336,375.00 112,125.00 6. Total Work Completed 954,202.10 7. Deductions -4,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 950,202.10 351,501.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 351,501.40