Dept. of Trans.       PROGRESS   Serial No.  Contract No.                               
                                          09-022-06-00  06-0C8204                       
                PROGRESS PAYMENT VOUCHER  %complete:   %time:                           
Location:                                  32%          50%                             
06-TUL-63-22.6/ .0                    Federal Project:                                  
                                     STPL-6206(14)                                      
                             ACHS-P063(21)                                              
                             STPG-P063(21)                                              
Progress payment No. 03            Payment period ending: 01-20-09                      
LEE'S PAVING INC                                                                        
1212 N PLAZA DRIVE                                                                      
VISALIA CA 93291                                                                        
                                                                                        
                                                                                        
Escrow No.  00000                                                                       
                                    Total Estimate   This Estimate                      
1. Contract Itms Without Mobil.         145,770.63       79,101.45                      
2.a. Extra Work                                                                         
  b. Adjustment Comp.                                                                   
3. Materials on Hand                                                                    
4. Earned Subject to Retention          145,770.63       79,101.45                      
5. Mobilization                          69,350.00       14,600.00                      
6. Total Work Completed      215,120.63                                                 
7. Deductions                            -8,154.34       -1,716.70                      
8. a.Contract Retentions                                                                
   b. Unsatisfactory Prog.                                                              
   c. Reduction after 95% Comp.                                                         
9. Total pay to Contractor              206,966.29       91,984.75                      
10. Reduction Amt to Escrow                                                             
11. Payment to Escrow             0.00                                                  
12. Net Pymt. this Estimate                              91,984.75