Dept. of Trans. PROGRESS Serial No. Contract No. 25-237-17-57 06-1G8104 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 10% Location: Federal Project: 06-TUL-63-R19.2/R24.3 NONE Progress payment No. 001 Payment period ending: 08-20-25 ARCHER CIVIL CONSTRUCTION LLC 1353 SOUTH J ST TULARE CA 93274 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 485,806.80 485,806.80 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 485,806.80 485,806.80 5. Mobilization 6. Total Work Completed 485,806.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 485,806.80 485,806.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 485,806.80