Dept. of Trans.             PROGRESS              Serial No.    Contract No.
                                                  19-053-12-55  07-1193U4
                    PROGRESS PAYMENT VOUCHER      %complete:    %time:
                                                    63%           41%

Location:                                         Federal Project:
07-LA-10-37.2/42.4                                NHPI-010-1(829)
                                                  CMLN-6207(70)

Progress payment No. 038                     Payment period ending: 02-20-19
GUY F ATKINSON CONSTRUCTION
LLC
18201 VON KARMAN AVE #800
IRVINE CA 92612

Escrow No. 00000
                                           Total Estimate      This Estimate
 1. Contract Itms Without Mobil.            88,819,118.89       1,262,010.64
 2. a. Extra Work                            6,823,915.41         142,643.12
    b. Adustment Comp.                         958,922.91          26,504.21
 3. Materials on Hand                        2,075,428.47          -2,803.47
 4. Earned Subject to Retention             98,677,385.68       1,428,354.50
 5. Mobilization                            16,162,297.00               0.00
 6. Total Work Completed    112,764,254.21
 7. Deductions                                 -17,750.00               0.00
 8. a. Contract Retentions
    b. Unsatisfactory Retentions
    c. Reduction after 95% Comp.
 9. Total pay to Contractor                114,821,932.68       1,428,354.50
10. Reduction Amt to Escrow
11. Payment to Escrow                 0.00
12. Net Pymt. this Estimate                                     1,428,354.50