Dept. of Trans.       SEMI-FINAL   Serial No.  Contract No.                             
                                          01-019-09-22  07-125604                       
                PROGRESS PAYMENT VOUCHER  %complete:   %time:                           
Location:                                 100%         100%                             
07-LA-14-33.4/44.0                    Federal Project:                                  
                                     CMLN-6207(14)                                      
                             STPL-6207(14)                                              
                             N-6207(14)                                                 
Progress payment No. 57            Payment period ending: 02-16-00                      
FCI CONSTRUCTORS                                                                        
12707 HIGH BLUFF DRIVE STE 13                                                           
SAN DIEGO CA 92130                                                                      
                                                                                        
                                                                                        
Escrow No.  00848                                                                       
                                    Total Estimate   This Estimate                      
1. Contract Itms Without Mobil.      23,473,926.47            0.00                      
2.a. Extra Work                       4,417,708.39        3,563.18                      
  b. Adjustment Comp.                   778,818.51       28,677.76                      
3. Materials on Hand                                                                    
4. Earned Subject to Retention       28,670,453.37       32,240.94                      
5. Mobilization                       2,714,000.00            0.00                      
6. Total Work Completed   31,384,453.37                                                 
7. Deductions                           -13,536.42            0.00                      
8. a.Contract Retentions             -1,415,103.63            0.00                      
   b. Unsatisfactory Prog.                                                              
   c. Reduction after 95% Comp.       1,415,103.63            0.00                      
9. Total pay to Contractor           31,370,916.95       32,240.94                      
10. Reduction Amt to Escrow          -1,415,100.00            0.00                      
11. Payment to Escrow     1,415,100.00                                                  
12. Net Pymt. this Estimate                              32,240.94