Dept. of Trans.             PROGRESS              Serial No.    Contract No.
                                                  20-357-16-24  07-304204
                    PROGRESS PAYMENT VOUCHER      %complete:    %time:
                                                    80%           39%

Location:                                         Federal Project:
07-LA-10-R2.1/R11.1                               HSIM-010-1(850)

Progress payment No. 013                     Payment period ending: 12-20-20
SPECTRUM CONSTRUCTION GROUP
INC
16 GOODYEAR #140
IRVINE CA 92618

Escrow No. 00000
                                           Total Estimate      This Estimate
 1. Contract Itms Without Mobil.             2,272,518.98          68,935.86
 2. a. Extra Work                               89,477.02          32,404.32
    b. Adustment Comp.
 3. Materials on Hand
 4. Earned Subject to Retention              2,361,996.00         101,340.18
 5. Mobilization                               297,000.00               0.00
 6. Total Work Completed      2,658,996.00
 7. Deductions
 8. a. Contract Retentions
    b. Unsatisfactory Retentions
    c. Reduction after 95% Comp.
 9. Total pay to Contractor                  2,658,996.00         101,340.18
10. Reduction Amt to Escrow
11. Payment to Escrow                 0.00