Dept. of Trans. PROGRESS Serial No. Contract No. 25-202-15-08 07-339604 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 66% Location: Federal Project: 07-LA-14-R29.0/R29.5 ACNH-P014(107) Progress payment No. 024 Payment period ending: 07-20-25 SUKUT CONSTRUCTION INC 4010 WEST CHANDLER AVENUE SANTA ANA CA 92704 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,666,426.29 6,500.00 2. a. Extra Work 149,037.64 12,063.38 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 15,815,463.93 18,563.38 5. Mobilization 500,000.00 0.00 6. Total Work Completed 16,315,463.93 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,315,463.93 18,563.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,563.38