Dept. of Trans. PROGRESS Serial No. Contract No. 25-237-13-27 07-4X9704 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 0% Location: Federal Project: 07-LA-1-42.4 PTNH-P001(694) Progress payment No. 001 Payment period ending: 08-20-25 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,000.00 31,000.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 31,000.00 31,000.00 5. Mobilization 6. Total Work Completed 31,000.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,000.00 31,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,000.00