Dept. of Trans. PROGRESS Serial No. Contract No. 25-203-15-06 10-0Y7704 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 99% Location: Federal Project: 10-MPA-140-12.0/22.1 ACNH-P140(41) Progress payment No. 012 Payment period ending: 07-20-25 GEORGE REED INC PO BOX 4760 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,560,545.95 0.00 2. a. Extra Work 1,436,682.79 588,877.92 b. Adustment Comp. -1,383,173.95 0.00 3. Materials on Hand 4. Earned Subject to Retention 13,614,054.79 588,877.92 5. Mobilization 550,000.00 0.00 6. Total Work Completed 14,164,054.79 7. Deductions -417,893.15 -327,893.15 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,746,161.64 260,984.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 260,984.77