Dept. of Trans. PROGRESS Serial No. Contract No. 25-203-13-17 10-1F9704 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 18% Location: Federal Project: 10-VAR NONE Progress payment No. 002 Payment period ending: 07-18-25 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,950,682.00 1,107,470.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,950,682.00 1,107,470.00 5. Mobilization 750,000.00 250,000.00 6. Total Work Completed 2,700,682.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,700,682.00 1,357,470.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,357,470.00