Dept. of Trans. PROGRESS Serial No. Contract No. 25-198-16-16 11-2N2344 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 11% Location: Federal Project: 11-SD-15-0.4/T2.8 NONE Progress payment No. 001 Payment period ending: 07-20-25 HAZARD CONSTRUCTION ENGR LLC 10529 VINE ST LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,039,133.00 1,039,133.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,039,133.00 1,039,133.00 5. Mobilization 213,750.00 213,750.00 6. Total Work Completed 1,252,883.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,252,883.00 1,252,883.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,252,883.00