Dept. of Trans. PROGRESS Serial No. Contract No. 25-202-15-06 11-431274 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 11% Location: Federal Project: 11-SD-5-R0.3/R36.0 NONE Progress payment No. 004 Payment period ending: 07-20-25 KIEWIT INFRASTRUCTURE WEST CO. 4650 BUSINESS CENTER DR FAIRFIELD CA 94534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,316,821.52 2,926,478.16 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 6,316,821.52 2,926,478.16 5. Mobilization 4,251,714.50 0.00 6. Total Work Completed 10,568,536.02 7. Deductions -305,749.70 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,262,786.32 2,921,478.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,921,478.16