Dept. of Trans.             PROGRESS              Serial No.    Contract No.
                                                  24-143-13-03  12-0R5004
                    PROGRESS PAYMENT VOUCHER      %complete:    %time:
                                                    84%           57%

Location:                                         Federal Project:
12-ORA-55-0.6/0.6                                 HSNH-P055(66)

Progress payment No. 005                     Payment period ending: 05-20-24
INTERNATIONAL LINE BUILDERS,
INC.
3955 TEMESCAL CYN RD
CORONA CA 92883

Escrow No. 00000
                                           Total Estimate      This Estimate
 1. Contract Itms Without Mobil.               820,915.82               0.00
 2. a. Extra Work                               38,215.80               0.00
    b. Adustment Comp.
 3. Materials on Hand
 4. Earned Subject to Retention                859,131.62               0.00
 5. Mobilization                                51,258.00               0.00
 6. Total Work Completed        910,389.62
 7. Deductions                                       0.00          10,000.00
 8. a. Contract Retentions
    b. Unsatisfactory Retentions
    c. Reduction after 95% Comp.
 9. Total pay to Contractor                    910,389.62          10,000.00
10. Reduction Amt to Escrow
11. Payment to Escrow                 0.00
12. Net Pymt. this Estimate                                        10,000.00